PM Surya Ghar Last Date: Install by 31 March 2027, and the New Rule That Archives Inactive Applications from 30 November 2026
Published · By Karthikeyan E, R K Solar Solutions, Coimbatore

The PM Surya Ghar last date has two parts now. The scheme itself runs till 31 March 2027. And from 30 November 2026, the Ministry of New and Renewable Energy (MNRE) will archive applications that are sitting idle on the portal. Applied in Coimbatore and not yet picked a vendor? Or picked one and not yet installed? This page gives you the exact dates and what to do before each one.
The short answer
| Step | Last date | Where it comes from |
|---|---|---|
| Choose a vendor after applying | 15 days from the application date | MNRE OM, 23 Nov 2026, para 3(a) |
| Complete installation and submit it on the portal | 45 days from the vendor selection date | MNRE OM, 23 Nov 2026, para 3(b) |
| First archiving of idle applications | 30 November 2026, then every 10 days in December | MNRE OM, 23 Nov 2026, para 3(c) |
| Installation details on the portal for the central subsidy | 31 March 2027 | MNRE OM, 23 Nov 2026, para 5 |
| New applications | No fixed date. The portal closes once active applications reach 1 crore | MNRE OM, 23 Nov 2026, para 4 |
| Tamil Nadu state top-up (up to Rs 22,000) | No date. First 1,00,000 eligible applicants | G.O. 102 |
One line to remember: apply, pick a vendor the same week, and get the panels up within a month and a half. Then the 31 March 2027 date takes care of itself.
What MNRE said on 23 November 2026
MNRE issued an Office Memorandum, file number 318/17/2024-GCRT-Part(17), on 23 November 2026. It is addressed to all states, all DISCOMs on the National Portal and all empanelled vendors. The main points, in plain words:
- The target is rooftop solar on 1 crore homes by 31 March 2027.
- More than 91 lakh applications have come in on the National Portal. About 68 lakh consumers have already got the benefit.
- A large number of applications are stuck at one stage for a long time. They take up space in the active list.
- So from 30 November 2026, idle applications will be archived, in rounds.
- REC Ltd, which runs the portal, will make the changes needed.
- The memorandum was published on the portal under What Is New on 24 November 2026. The portal home page now shows a countdown: Scheme closes on 31 March 2027.
Archived is the word the memorandum uses. In practice it means the application is taken out of the active list. It is not a rejection, and it is not a ban. You can apply again, but you start from zero. The full text is in the memorandum PDF (284 KB).
The 15-day rule: choose a vendor within 15 days of applying
After you submit the application on pmsuryaghar.gov.in, the portal asks you to select an empanelled vendor. Many people stop here. They apply, get the feasibility approval, and then wait for quotes for weeks.
From 30 November 2026, an application with vendor selection pending for more than 15 days from the submission date will be archived.
In Coimbatore this is the stage where most delays happen. People compare three or four quotes, wait for a relative to visit, or wait for the roof to be free. All of that is fine, but do it before you apply, not after. Once you submit, the 15-day clock starts.
The 45-day rule: install within 45 days of choosing a vendor
Once a vendor is selected, the vendor has to complete the installation and submit the installation details on the portal within 45 days. If that is not done, the application is archived.
Note which date the 45 days start from. It is the vendor selection date, not the application date. If you applied on 1 December and picked a vendor on 10 December, the installation must be on the portal by 24 January.
What can eat into the 45 days:
- Panel stock. DCR panels of the size you want may take a week or two to arrive.
- Roof work. A water-proofing job or a parapet wall change before the structure goes up.
- Payment. The vendor will not order material until the first instalment is paid.
- Rain. A few days of heavy rain in Coimbatore in November and December can stop roof work.
In our own work we complete every stage up to installation within 10 days of vendor selection. The case we documented in detail took 19 days from application to installation (applied 21 August 2026, installed 9 September 2026). Both are well inside the 45-day limit. The limit is comfortable if the vendor has stock and the customer is ready.
Archiving dates: 30 November, 10, 20 and 30 December 2026
| Round | Date | Which applications |
|---|---|---|
| 1 | 30 November 2026 | Vendor selection pending for more than 15 days, or installation pending for more than 45 days after vendor selection, as on that date |
| 2 | 10 December 2026 | Same test, on the updated portal data |
| 3 | 20 December 2026 | Same test |
| 4 | 30 December 2026 | Same test |
Two things the memorandum says clearly:
- No separate communication will go to anyone. There will be no SMS or email before the archiving. You have to check your own status on the portal.
- MNRE may shorten the 15 and 45 days later. The memorandum says it will reassess and may prescribe a narrower timeline.
How to check: log in at pmsuryaghar.gov.in with your registered mobile number and open Consumer Login. The stage shown there is what MNRE will look at. Our status and timeline post explains each stage.
Who is not covered
The 23 November 2026 order applies to applications that are:
- Not under the ULA model. ULA stands for Utility Led Aggregation, where the DISCOM arranges the installation in bulk. In Tamil Nadu almost all home applications are the regular, consumer-chooses-vendor type, so they are covered.
- Not taking a bank loan through JanSamarth. If you applied for the PM Surya Ghar loan on the JanSamarth portal, this round of archiving does not touch your application.
If you are paying from savings, or through a bank loan arranged outside JanSamarth, the rule applies to you.
Application archived? How to apply again and what you lose
The memorandum says the consumer is free to re-submit the archived application. But read the next line carefully. The new submission is a fresh application. It has no link to the old one.
What that means in practice:
- You lose the original application date. Your place in the queue is gone.
- Whether the TNPDCL feasibility approval has to be done again is not stated in the memorandum. TNPDCL will clarify this. Ask your section office before you re-apply.
- If the portal has reached the 1 crore cap by then, you may not be able to submit at all until space opens up.
- You still need installation details on the portal by 31 March 2027. A fresh application in late January leaves very little room.
So the cheapest option is to not get archived in the first place. Pick the vendor now, and fix the installation date in writing.
31 March 2027: what must be on the portal by then
The scheme period ends on 31 March 2027. Para 5 of the memorandum says:
- All installations must be completed and the details submitted on the National Portal by 31 March 2027 to be eligible for the central subsidy (CFA).
- From 1 April 2027, the portal will not accept installation completion details.
- Vendors are told to accept orders only when they can guarantee installation submission before 31 March 2027.
Note what is not said. The inspection, the net meter and the subsidy credit can happen after 31 March 2027, as long as the installation itself is on the portal before that date. In our Coimbatore cases the gap from installation to central credit has been about four weeks (28 days in the documented case). So an installation submitted in the last week of March should still get the credit in April or May.
Central subsidy amounts have not changed: Rs 30,000 per kW for the first 2 kW and Rs 18,000 for the third kW, so Rs 78,000 for 3 kW and above. See the subsidy amounts for Tamil Nadu.
What this looks like in Coimbatore
We are an empanelled vendor under PM Surya Ghar and with TNEB, based in Coimbatore. On 19 November 2026 our vendor dashboard showed 639 applications approved through us, 586 installed and 525 with the subsidy approved. The full numbers and a dated timeline are in a separate post. Here is how our stage times compare with the new limits:
| Stage | MNRE limit from 30 Nov 2026 | Our usual time in Coimbatore |
|---|---|---|
| Application to vendor selection | 15 days | Same day when we file the application |
| Vendor selection to installation submitted | 45 days | Within 10 days; 19 days from application in the documented 6 kW case |
| Installation to central subsidy credit | No limit, but installation must be on the portal by 31 Mar 2027 | About 4 weeks; 28 days in the documented case |
If you applied before 30 November 2026
Log in today and look at the stage. If it says vendor selection pending and your application is older than 15 days, you are in the first round. Select a vendor before 30 November. If you have selected a vendor and the installation is not done, call the vendor and ask for the installation date in writing. If the vendor cannot give one, you can change the vendor on the portal, but only until the agreement is uploaded. Once the agreement is uploaded, the vendor cannot be changed.
If you apply in December 2026 or January 2027
Count backwards from 31 March 2027. Allow 45 days for installation and a week for the portal update. That means a vendor selected by mid February 2027 is the practical limit for a safe installation. Apply before that, and apply only when the roof, the money and the vendor are ready.
We install across the Coimbatore region. The TNPDCL net meter step is handled by the local section office for your area, and our team files it for you.
Tamil Nadu state Rs 22,000: is there a last date?
The Tamil Nadu state top-up under G.O. 102 is up to Rs 22,000 for 3 kW and above. The order does not give a last date. It is limited to the first 1,00,000 eligible applicants in the state.
The state amount is paid only after the central subsidy is credited. The beneficiary data goes from the National Portal to TNGECL, then to TEDA for sanction. So the 31 March 2027 date matters for the state amount too. If your central subsidy is not done, the state amount cannot start. Our first state credit came 41 days after the central credit, as documented in the G.O. 102 post.
Checklist with dates for a Tamil Nadu applicant
- Before applying: get quotes, check the roof, decide the size, arrange the money. Do not submit until these are done.
- Day 0: register on pmsuryaghar.gov.in with your TNPDCL consumer number. The 11-step guide has screenshots.
- By day 15: select the vendor on the portal. Ask the vendor to confirm the selection shows on their dashboard.
- By day 45 after vendor selection: installation complete and submitted on the portal by the vendor. Get the submission date from the vendor.
- Next 1 to 2 weeks: TNPDCL inspection, net meter application and meter fixing.
- Then: bank details and the subsidy claim. Central credit usually within 15 working days of the claim.
- After the central credit: nothing to do for the state amount. TNGECL picks up the data and pays by NEFT.
- Hard date: installation on the portal before 31 March 2027. Nothing after that gets the central subsidy.
Questions people ask
What is the last date to apply for PM Surya Ghar?
There is no separate last date to apply. The scheme runs till 31 March 2027, and the portal stops taking new applications once active applications reach 1 crore. Installation details must be on the portal by 31 March 2027, so a practical last date to apply in Coimbatore is early February 2027.
What is the last date for the PM Surya Ghar subsidy?
Installation details must be submitted on the National Portal by 31 March 2027 to get the central subsidy. The portal will not accept installation completion from 1 April 2027. The subsidy itself is paid after inspection and net meter, which can be a few weeks later.
What does archived mean on the PM Surya Ghar portal?
Archived means MNRE has removed the application from the active list. It happens when no vendor was chosen within 15 days of applying, or when installation was not submitted within 45 days of choosing a vendor. The consumer can apply again, but it counts as a fresh application with a new date.
The 15 days are counted from which date?
From the date the application was submitted on the National Portal. If no vendor is selected within 15 days of that date, the application is archived in the next round. The rounds are 30 November, 10 December, 20 December and 30 December 2026.
The 45 days are counted from which date?
From the date the vendor was selected on the portal, not from the application date. Installation must be completed and submitted on the portal within 45 days of that date.
Does the archiving rule apply to bank loan applicants?
No. The 23 November 2026 memorandum covers applications that are not under the ULA model and that have not taken a bank loan through the JanSamarth portal. Loan applicants and ULA applications are outside this round of archiving.
Can I apply again on the same roof after my application is archived?
Yes. The memorandum says the consumer is free to re-submit. The new application gets a new date, goes to the back of the queue and must still finish installation before 31 March 2027. It also needs the portal to be below the 1 crore cap.
Is there a last date for the Tamil Nadu state subsidy of Rs 22,000?
G.O. 102 does not give a date. The state top-up goes to the first 1,00,000 eligible applicants in Tamil Nadu. Since it is paid after the central subsidy, your central subsidy must be done by 31 March 2027 for the state amount to follow.
Sources
- MNRE Office Memorandum F. No. 318/17/2024-GCRT-Part(17), dated 23 November 2026, Implementation of phased archiving of inactive applications under PM Surya Ghar: Muft Bijli Yojana (copy of the PDF, 284 KB). Listed under Scheme Guidelines/Framework on the PM Surya Ghar portal, What Is New, dated 24.11.2026 there. The portal opens the file through a short-lived download link, so we keep a copy.
- PM Surya Ghar National Portal, What Is New. Official listing of the memorandum.
- PM Surya Ghar National Portal, Consumer Login. Where the application stage is shown.
- MNRE scheme guidelines, order No. 318/17/2024-Grid Connected Rooftop dated 16 March 2024. Scheme period till 31 March 2027.
- Government of Tamil Nadu, G.O. (Ms) No. 102, Energy Department, state top-up subsidy, explained on this site
- R K Solar Solutions vendor dashboard on the PM Surya Ghar portal, 19 November 2026. Source of the Coimbatore day counts.
- Mercom India, MNRE to Archive Inactive PM Surya Ghar Applications, 24 November 2026
This page will be updated if MNRE changes the 15-day or 45-day limits or the archiving dates. Last checked 26 November 2026.
About the author
Karthikeyan E runs R K Solar Solutions in Coimbatore and has been installing rooftop solar since 2011. His team files the PM Surya Ghar registration, the TNPDCL net meter application and the subsidy claim for every customer. Empanelled vendor under PM Surya Ghar and with TNEB; more than 580 installations across Tamil Nadu, with 525 PM Surya Ghar subsidies credited to customers as on 19 November 2026. Learn more about Karthikeyan E →